Tentative Project Timeline
Stanford Medicine is excited to share our proposed timeline for bringing a new, world-class cancer center to the Redwood City community.
Before a project like this can be built, it goes through a public review and approval process with the City of Redwood City. This ensures the project is a good fit for the community and meets all City requirements for design, safety, and environmental standards.
This timeline outlines the key milestones in this process. Please note that the timing of these events are our best estimates and are subject to change. We are committed to partnering with the city and the community every step of the way.
2025
- October
- Community Open Houses
2026
- February
- Community Open Houses
- Spring
- Application to initiate Amendments to City’s General Plan and Stanford in Redwood City Precise Plan
- Early Summer
- Project Plan Submittal
- Submission of Technical Studies for CEQA
- Summer
- City Council Consideration to Amend General Plan and Precise Plan
- Community Open Houses
2027
- City Starts Project Environmental Review (CEQA) (Timing controlled by City)
2029
- Completion of CEQA Review (Timing controlled by City)
- City Consideration of Project Approvals (Timing controlled by City)
2030+
- Groundbreaking
- Construction
- Patient Day 1